Project Overview
New stand alone credit union, much of the façade is cladded in Hoover Reynobond aluminum composite panels, rain screen system, Anodic Clear for some of it, and a Pewter color for the canopy wraps. Working with the Cork Howard team was a pleasure.
Location: Rome, GA
Completion Date: June 2026
Project Duration: 3.5 Weeks
General Contractor: Cork Howard
Architect: Appleby Russo
PCG Project Manager: Jesse Rose
Challenges and Solutions
Job went well, a couple of challenges here and there, but to be expected.
Results
Job looks really good, clean, correct panel directions to maintain similar color finish throughout.
Frequently Asked Questions
Was there anything special about this job that highlights PCG’s custom fabrication capabilities?
Some changes to panel sizes based on field conditions. Always allows us to respond quickly to changes in the field.