Gravel 85 Distribution Center

Project Overview

Located in Buford, Georgia, the Gravel Springs Logistics Center project consisted of two large-scale industrial buildings requiring custom architectural canopy systems. Our scope included the design, fabrication, and installation of both bullnose dock canopies and architecturally distinct entry canopies featuring aluminum composite material (ACM) fascia panels.

We worked closely with The Conlan Company, the general contractor, to deliver a custom color solution that aligned with the client’s brand identity. The project demanded precision, speed, and coordination—culminating in a successful, on-time delivery within just 4.5 weeks.

Location: 2323 Brown Road, Buford, GA 30519
Completion Date: January 2023
Project Duration: 4.5 weeks
General Contractor: The Conlan Company
PCG Project Manager: Blake Dodson
Total Installed Coverage: 1,720 linear feet of bullnose dock canopies; 443 linear feet of entry canopies

Entry Canopy System – Technical Specifications

Primary Components:

  • .050" roll-formed gutter
  • .028" aluminum canopy panels
  • 4mm ACM fascia and soffit panels

Support Structure: Structural steel C-beams and steel outriggers
Projection: 1’-8” from building wall
Height: 14’-0” above finished floor
Finish: PVDF Kynar 500 “Clarion Orange” – custom color to match client branding
Drainage: Integrated gutter system with scupper drainage
Wind Load Rating: Engineered for 110 mph

Bullnose Dock Canopy System – Technical Specifications

Primary Components:

  • .050" roll-formed gutter
  • .028" aluminum canopy panels
  • .032" bullnose fascia

Support Structure: Galvanized steel framework (22ga hat & 18ga channel)
Projection: 3’-11” from building wall
Height: 16’-0” above truck court
Finish: PVDF Kynar 500 – Dark Bronze
Drainage: Integrated gutter system with scupper drainage
Wind Load Rating: Engineered for 110 mph

Installation Process

  1. Site survey and structural verification
  2. Custom fabrication of all canopy system components
  3. Installation of structural supports: wall gutter, outriggers, and C-beams
  4. Canopy panel installation
  5. Final assembly: front gutter, fascia, soffit panels, end caps, and trim detailing

Project Outcomes

Functionality: Provided effective weather protection for loading and unloading operations
Aesthetic Value: Enhanced the facility’s visual appeal and brand consistency through architectural finishes
Efficiency: Completed within 4.5 weeks without delays

Safety Performance

  • Zero incidents throughout the project duration
  • 100% OSHA compliance
  • Daily safety briefings conducted
  • Full PPE compliance from start to finish

Summary

The Gravel 85 Distribution Center project exemplifies our ability to deliver custom-engineered canopy systems that balance aesthetics, structural integrity, and performance. Our collaboration with The Conlan Company ensured seamless integration with the overall building design—resulting in a visually striking, highly functional industrial facility.