Project Overview

Clayton 75 is an industrial warehouse project located in Jonesboro, GA. Our scope of work on this project was installing approximately 2,160 linear feet of 24” bullnose fascia canopies over the dock doors and aluminum composite panels at the SE & SW entrances.

Location: 2464 Mt. Zion Rd. Jonesboro, GA 30236
Completion Date: August 2023
Project Duration: 10 weeks
Total Coverage Area: 2,160 linear feet of dock canopies
 - Approximately 2,400 SF of ACM panels
General Contractor: Hillwood Construction Services
PCG Project Manager: Keenan Hale

Project Scope

ACM Technical Specifications

  • Primary System: Reynobond 4mm Fire Resistant Core Aluminum Composite Panels (ACM)
  • Support Structure: 5/8” plywood sheathing
  • Finish: PVDF Kynar 500 “Anodic Clear”

ACM Installation Process

  1. Site visit prior to installation for panel dimension measurements
  2. Custom fabrication of panels in our shop with CNC machine
  3. Field install continuous extrusions to perimeter of panels
  4. Panel installation with clip to extrusion system
  5. Caulk all panel joints to ensure water tight system

Dock Canopy Technical Specifications

  • .050” roll-formed gutter
  • .018” corrugated deck panel with 16” coverage
  • .032 aluminum bullnose fascia 24” tall

Dock Canopy Installation Process

  1. Shop fabrication of framing members consisting of 22ga hat section & 18ga channel
  2. Shop fabrication of 18ga brackets
  3. Shop fabrication of curved bullnose fascia from flat stock
  4. Field attach continuous gutter and framing members to solid tilt panel with expansion anchors
  5. Install front gutter, deck pans and fascia to complete installation

Unique Project Challenge

Typically, when we mobilize to install dock canopies, the truck court pad has already been poured, allowing us to use a scissor lift on a smooth concrete surface. We were asked to begin dock canopy installation before this was done so we had to work out of a telescopic boom lift. Although this slowed the rate of installation, we made up for it and got the job done.

Performance Results

  • Enhanced facility appearance
  • Provide coverage from rain at truck loading docks

Safety Statistics

  • Zero incidents during installation
  • 100% OSHA compliance
  • Full PPE compliance throughout project